A lawful development certificate is a legal document from your council confirming that what you plan to build is lawful, which for an extension means it does not need planning permission. You do not have to have one to build under permitted development, but it puts the answer in writing.
[DRAFT - wording to be approved by the client before launch.]
What it is
Anyone can apply to their local planning authority for a decision on whether a proposed development is lawful for planning purposes. If the council agrees, it issues the certificate, and building in line with it must be presumed lawful unless something material changes. It is not a replacement for planning permission: anything the certificate does not cover still needs permission if the rules say so.
The two kinds
- Proposed: for something you have not built yet. This is the one for an extension you are planning.
- Existing: for something already there, for example an extension built years ago without paperwork.
When it is worth having
- Your extension is close to a limit, and you want the council's answer before you spend on building.
- There is any doubt about whether permitted development applies to your house.
- You expect to sell. A buyer's solicitor will ask for evidence that the extension was lawful, and a certificate is that evidence.
What you send
- The application form for a proposed development.
- A plan identifying the land.
- A precise description of what you intend to build, with enough information for the council to judge it. In practice that means drawings.
- Your reasons for believing it is lawful.
- The fee.
The fee and the wait
For a proposed development the fee is half the normal planning fee. The council should decide within 8 weeks of validating the application.
Where drawings come in
The council can only certify what it can see, so the application stands on the drawings. They need to show the sizes that the limits are measured in: how far the extension goes back, how high it is, and how close it comes to the boundaries.
This guide describes England. In Northern Ireland the equivalent is a certificate of lawfulness of proposed use or development; see extensions in Northern Ireland.
Common questions
Is a lawful development certificate compulsory?
No. You can build under permitted development without one. It is there for certainty, and for proof when you sell.
How long does a lawful development certificate take?
The council should decide within 8 weeks of validating the application.
Is it the same as planning permission?
No. Planning permission is the council allowing something that needs its consent. A certificate is the council confirming that consent was never needed.
Last reviewed .
Sources
Read next
- Permitted development or planning permission: the size limits for extending without a planning application, and when you must apply.
- Prior approval for larger extensions: how to build up to 6 or 8 metres at the back without a full planning application.
- Can I extend my house?: five checks that tell you whether a house can be extended, including one you are thinking of buying.
More guides: how to plan an extension, what extension drawings cost, do I need an architect for an extension?, who can draw plans for an extension, indicative or surveyed drawings, garage conversion: planning permission, garden room: planning permission, extensions in Scotland, extensions in Wales, extensions in Northern Ireland, party wall agreements, how long planning permission takes, extension roof types.
See yours before you spend a penny
Tell us your address and what you have in mind, and we show you your own house with the extension on it. The renders are free, wherever you are in the UK.